......@@ -191,7 +191,7 @@ this values in the input signals.
The configuration and programming of the system is then a process, where you altertately
configure/program and test. The result i carefully debugged programs and a fast and efficiant
commissioning of the plant. It also result in better programs, and more thoroughly workt
through functions, beacause the feeback is greater in the create process that the construction
through functions, beacause the feedback is greater in the create process that the construction
of a process control system implies.
At the simulation and commissioning it is of greate importance to have access to tools that
......@@ -2368,7 +2368,7 @@ Besides transfering a signal value, the connections also determine the execute o
different function blocks. If two objects are connected trough an output and an input,
normally the output-object is to be executed before the input-object. But sometimes a feedback
is needed in the net, and then you face a execute order loop. To determine the execute order
you have to specify the feeback with a connections of type ConFeebackDigtal or
you have to specify the feedback with a connections of type ConFeedbackDigital or
ConFeedbackAnalog. These are selected in the connection palette, viewed by activating
'View/Palette/Connection' in the menu. Under the folder 'ConPlc' you can find the feedback
connections. They are drawn with dashed lines.
......